Watch tower 44kWp PV Project

FSD Solutions was contracted to do the electrical installation of the carport 44kWp PV system at the Watch Tower head office in Krugersdorp during 2016.

The scope of work was as follow:-

  • Supply and install the complete DC and AC reticulation from the PV modules to the connection to the existing LV reticulation, as well as the complete earthing network.
  • Register the system with Metro and commission

We completed the work within the allocated budget and on time.