Liberty Water Project – Consulting Services

FSD Solutions was contracted, during 2017, to supply consulting services to Liberty, at their HO in Braamfontein, for their water project

The scope of work was as follow:-

  • Investigate the current water usage for the building with the view to reduce usage before embarking on the project
  • Implement water saving initiatives with M&V protocol
  • Calculate water usage profile to determine size of potable and rainwater storage tanks to be erected.
  • Calculate possible grey water harvesting to determine size of recycled grey water tank on roof
  • Investigate the position for potable, rain and grey water storage tanks with project team
  • Finalise the sizes of the respective water storage tanks – potable water 600 000L, rainwater 300 000L and grey water 25 000L
  • Obtain benchmark prices for the different options to finalise capital budget for approval
  • Draft RFP document with project team
  • Project manage complete project over 5 months duration

Project was completed on time and within the allocated budget framework.